1
|
- Council Transportation and Environment Committee
- Prepared by
- Public Works and Transportation
- Transportation Programs – Interagency Coordination
- January 9, 2006
|
|
2
|
- Review the Statewide Transportation Enhancement Program (STEP) and staff
recommendations for the current call for projects
- Discuss schedule for approval and submission of projects
|
|
3
|
- SAFETEA–LU was authorized on August 10, 2005 – retains the Enhancement
Program initiated in ISTEA and TEA–21
- 10% of Surface Transportation Program funds are set aside for
Enhancements
- STEP Funding level has not been released by TxDOT
- Project will be 80% federal and 20% local funding
- Projects must be submitted thru NCTCOG
|
|
4
|
- Bicycle and pedestrian
- Restoration/operation of historic trolley
- Restoration/operation of historic transit station
- Acquisition of historic RR right of way
- Landscaping transportation facilities
- Visitor center
- Control or removal of outdoor advertising
|
|
5
|
- Submit projects with congressional earmarks
- Submit trail projects submitted to Dallas County in their last MCIP call
for projects and request a letter of support from Dallas County
- Submit removal of outdoor advertising (billboards) projects for current
TxDOT projects
|
|
6
|
- Woodall Rodgers pedestrian deck received a $10 million Congressional
earmark for STEP funding
- $8 million STEP funds / $2 million local funds
- Local match could come from public or private funds
- STEP application must still be submitted
|
|
7
|
- East Dallas Veloway grade separated crossing of DART’s Southeast LRT
line received an $800,000 Congressional earmark
- Federal funding is not sufficient to complete the crossing
- Submit STEP application to address the shortfall
|
|
8
|
- Runyon Creek Greenbelt Trail - Wagon Wheels to UNT Campus
- Scyene Trail - Jim Miller near Piedmont to Prairie Creek Road at UP
Railroad
- Chalk Hill Trail - Pinnacle Park to Westmoreland at Illinois
- Cottonbelt Trail – Dallas North Tollway to Hillcrest
|
|
9
|
- East Dallas Veloway Phase 3 - Lakewood Blvd to DART LRT near Mockingbird
& Fisher
- East Dallas Veloway Phase 4 - Northwest Highway to White Rock Creek
North of Royal
- Lake Highlands Trail - White Rock Creek at Skillman to Lake Highlands
High School
- Northaven Trail Phase 1 - Dallas North Tollway to US 75
|
|
10
|
- TxDOT requires City to pay additional cost associated with billboard
removal resulting from application of more stringent City ordinances
- Submit STEP applications for projects where TxDOT is actively involved
in right of way acquisition:
- I-35E from I-635 to Loop 12
- Loop 12 Interchange at I-30
|
|
11
|
- TXDOT issued Call for projects 11/1/05
- Council Resolution 2/8/06
- Nominations due to NCTCOG 2/17/06
- Evaluation/ranking by NCTCOG 3/7/06
- RTC action on evaluations 4/13/06
- Nominations due to TXDOT 4/28/06
- Project selection by TXDOT 12/06
|